Schedule Updates as of 7/15/24
Reach 9 – Broadview from Cermak Road to 19th Street
- Construction began mid-December 2023 and will continue through mid 2024
- Tree clearing complete
- Excavation and Gabion mattress installation ongoing through May 2024
- Restoration to occur early summer 2024.
Reach 8 – Westchester from Gardner Road to Roosevelt Road
- Construction began January 2024 and will continue through end of 2024
- Tree clearing complete
- Drilled shaft installation and retaining wall construction ongoing through September of 2024
- Excavation and gabion installation to occur April through September 2024
- Pavement restoration to occur October 2024.
Reach 7 – Westchester from Roosevelt Road to Wedgewood Drive
- Construction began February 2024 and will continue through mid 2024
- Tree clearing to be complete.
- Excavation and gabion installation to occur July through Fall.
- Restoration to occur October 2024.
Reach 6 – Bellwood from Eastern Ave to Cernan Drive
- Harrison Street closed on February 5th and will remain closed through mid 2025
- Construction began mid-February 2024 and will continue through mid 2025
- Electrical removals and utility relocation in progress
- Proposed utility installation in progress
- Channel improvements to commence upon existing utility relocation.
- Pavement installation anticipated for October 2024
- Restoration and opening of Harrison and new roadway north of creek anticipated for Summer 2025
Reach 5 – Bellwood South of St. Charles Road
- Construction began March of 2024 and will continue through November 2024
- Tree clearing complete
- Drilled shaft installation and retaining wall construction anticipated from mid-April through September 2024
- Excavation and gabion installation to occur June through September 2024
- Pavement restoration to occur October 2024
Reach 4 – Bellwood North of St. Charles Road
- Construction to begin March of 2024 and will continue through November 2024
- Tree clearing complete
- Excavation and gabion installation to occur June through September 2024
- Restoration to occur October 2024
Reach 3 – Melrose Park South of Lake Street near UPRR Proviso Facility
- Construction to begin May of 2024 and will continue through April 2025
Reach 2 – Stone Park between Mannheim Road and Lake Street
- Construction began March of 2024 and will continue through August 2025
- Tree clearing began March 2024 through end of April 2024
- Establish access and performed removals through May 2024
- Utility work to began May 2024 through November 2024
- Drilled shaft and retaining wall construction to begin June 2024 through June 2025
- Excavation and gabion installation to occur from September 2024 through June 2025
- Pavement restoration to occur in August of 2025
Reach 1 – Stone Park and Northlake between Mannheim Road and E Hirsch Street
- Construction began March of 2024 and will continue through August 2025
- Pavement and fence work near south of 43rd to occur in July 2025
- Excavation to begin August 2024
- Drilled shaft installation and retaining wall construction to begin August 2024 and continue through April 2025
- Park construction to be complete in August 2025
- Pavement restoration to be complete in August 2025