Schedule Updates as of 05/02/25

Reach 9 – Broadview from Cermak Road to 19th Street

  • Construction began mid-December 2023 and will continue through Summer of 2025
  • Restoration to occur in Spring 2025.

Reach 8 – Westchester from Gardner Road to Roosevelt Road

  • Construction began January 2024 and will continue through May2025
  • Excavation and gabion installation to occur September 2024 through May 2025
  • Pavement restoration on west side of creek to occur in May 2025

Reach 7 – Westchester from Roosevelt Road to Wedgewood Drive

  • Construction began February 2024 and will continue through August 2025
  • Excavation and gabion installation to occur May 2025 through September 2025.
  • Restoration to occur in September 2025.

Reach 6 – Bellwood from Eastern Ave to Cernan Drive

  • Construction began mid-February 2024 and will continue through fall of 2025
  • Lift station installation in progress.
  • Channel improvements to commence upon existing utility relocation.
  • Restoration and opening of Harrison and new roadway north of creek anticipated for Fall 2025

Reach 5 – Bellwood South of St. Charles Road

  • Construction began March of 2024 and will be completed after the utlity conflict, estimate of June 2025.
  • Pavement restoration on west side of Channel is delayed due to utility conflict.

Reach 4 – Bellwood North of St. Charles Road

  • Construction to begin March of 2024 and will continue through 2025
  • Excavation and gabion installation 85% complete
  • Completion is delayed due to utility conflict on north side of St. Charles Road
  • Restoration to be completed 2025.

Reach 3 – Melrose Park South of Lake Street near UPRR Proviso Facility

  • Construction began July of 2024 and will continue through 2025
  • Excavation and gabion installation in progress.

Reach 2 – Stone Park between Mannheim Road and Lake Street

  • Construction began March of 2024 and will continue through 2025
  • Drilled shaft and retaining wall construction ongoing through 2025
  • Excavation and gabion installation to finish by end of 2025
  • Pavement restoration to finish by end of 2025
  • Utility conflict likely to impact above dates

Reach 1 – Stone Park and Northlake between Mannheim Road and E Hirsch Street

  • Construction began March of 2024 and will continue through 2025
  • Drilled shaft installation and retaining wall construction is planned to start Summer of 2025.
  • Park construction to finish by end of 2025
  • Required plan modification likely to impact above dates.