Schedule Updates as of 10/01/2026
Reach 9 – Broadview from Cermak Road to 19th Street
- Construction completed. Vegetation maintenance & management work will continue through 2027.
Reach 8 – Westchester from Gardner Road to Roosevelt Road
- Construction completed. Vegetation maintenance & management work will continue through 2027
Reach 7 – Westchester from Roosevelt Road to Wedgewood Drive
- Construction completed. Vegetation maintenance & management work will continue through 2027
Reach 6 – Bellwood from Eastern Ave to Cernan Drive
- ACB Mat installation will be completed in October 2026.
- Lift Station installed and fully operational.
- Restoration and opening of Harrison and new roadway north of creek anticipated for in November 2026
Reach 5 – Bellwood South of St. Charles Road
- Construction completed. Vegetation maintenance & management work will continue through 2027
Reach 4 – Bellwood North of St. Charles Road
- Construction completed. Vegetation maintenance & management work will continue through 2027
Reach 3 – Melrose Park South of Lake Street near UPRR Proviso Facility
- Construction completed. Vegetation maintenance & management work will continue through 2027
Reach 2 – Stone Park between Mannheim Road and Lake Street
- Major construction work completed.
- Lift Station installation anticipated to be completed in October 2026.
Reach 1 – Stone Park and Northlake between Mannheim Road and E Hirsch Street
- Restoration work anticipated to be completed by October 2026
- Restoration work is underway.